We got this in early/mid July. Nothing since then. It's been more waiting. Eden Brae give themselves 20 working days to order things for our build - our 20 days will be up on Friday. 

We went through CDC rather than Council. We have been pegged for about a month now, and our EBH neighbours over the road got pegged just under a week ago. The concern for us is, will EBH wait til they catch up to us, and do our builds together? We have had that many delays so far (not entirely EBH's fault mind you!!), that we just want to get started. We chose all our colours in December - another concern. Will the tiles still be produced when we get around to needing them?

Anyway, maybe..MAYBE...we will have something on site by the end of next week? I don't know. In some ways I am completely over this building business. We bought the land 11 months ago and thought we would be in by Christmas for sure. Our CSO said realistically we could expect to be in by early March.


Tuesday, 9 July 2013

Survey and final plans ordered

This is what we've got at the moment. More grass...and just in time for the builders to come along and destroy it ;) We've gotten our commencement letter from the bank. We've signed off on all our variations and paid 5% of them. Our survey has been ordered (4.7.13) and we should have final plans to check over at some point this week.Once that's all approved we can organise our site start meeting with our CSA.



Here are a couple of our favourite pieces which will go into the new home. Brushed aluminium pendants for the kitchen (Beacon), wall clock almost as big as me (Splendour Interiors), our dining table (with the chairs that I hate!!) and foyer light (Masters).


As for the build, here is where we are up to. So much more to go! At least we are almost out of admin.

Fast forward one hour and we have received our final colours, PCV's and plans to check over :)

Saturday, 1 June 2013

Registered...so, what's next???



A few things have happened since I last wrote.
Most notably, our land registered on May 14. We extended our site start date to the end of July so that we would have enough time to get all of our admin completed. As soon as land registered, we ordered the s149 (2) from Camden Council (an Eden Brae requirement we were advised of when we had our contract signing). The s149(2) cost just over $50, so not too bad. Our land is expected to settle on June 4th.

Within one week (May 24), the fences were down and we could access our block. We noticed some blue spray paint on the block...thought maybe they were marking out where the trees would go; and one week later we had trees :) Not sure what they are but two look like they may be a kind of eucalypt, and the other two remind me of lilly pillies. One of them, we are convinced, has a drinking habit because it has a serious lean to it. We noticed they were digging up a section of our stage for footpaths so we shouldn't be too far behind for that either.

Today, while checking out the trees, and attending Cobbitty markets (which was AWESOME!), I met my first neighbours. They're from across-the-road, and are also building with Eden Brae. Shame we didn't know about them earlier, we could have compared notes :P Anyway they seemed lovely, and it was nice to meet another couple who are so excited about their build. We've also found out through the council website, that the block behind us is a single storey (WOOHOO!). We were a little worried about them being double. No big deal if they were, it just means a little more sunlight in our yard throughout the day.

In other news, another stage has come and gone in Oran Park Town. Speaking to one of the Greenfields guys, they had sold all but a handful of blocks (about 39 with holding deposits on the first day?). 

The next steps, as per our Eden Brae CSO:
1. CSO orders the CDC pre-assessment with this certificate which takes 5 working days, your file is then prepared for CDC lodgement.

2.      Receive CDC approval 

3.      Requesting the sign off for the DA Check letter – understanding you have not seen the final plans but this is to ensure you have raised all the variations you want to so far. We ask for you to look at your current plans to see if you may see something else you want. If not, you confirm no more changes.

4.      DA Check to be completed – this is an important check through your file from your contract to all the variations are check and ensure no doubles, errors or missed items. From this stage we are able to order your final plans and prepare your final documents. This is where all your variations will be reflected in the final plans. this process takes roughly 3-4 weeks.

5.      Site Start Appointment – this is where you will meet with me and go through final documents. I will send them to you before your appointment to have a look at before you come in. This will give you time and ensure you do not feel overwhelmed in the appointment. Can be done via email if needed.

6.      Surveyor Peg Out – Once we have your final plans we are able to order the surveyor peg out. The surveyor will out to site and peg the position of your slab ready for excavator to begin

7.      Bank’s Authority to Commence Construction (ACC) – during the above process we get your to engage with your bank to finalise all loans and ensure the funds are ready to draw down on. The bank will give Eden Brae Homes authority to commence construction. THIS MUST BE GIVEN PRIOR TO US COMMENCING WORKS.

8.     Production – once you have signed off all the final documents your file will go into production where all the orders are raised ready for the supervisor. Once this is complete you will be released into construction. This process takes approx 20-25 working days as per your contract.

She also sent us another letter and checklist, however this one was pretty simple - we have already taken care of most of it. She mentioned that our plans have been sent to Council, however we don't show up in Councils "Track your DA online" page just yet. Hopefully in the next few days.

I think that's enough for one entry, don't you? :O)

Monday, 6 May 2013

Money-Money-Money!!!

I'm going to give a shameless plug to our Senior Mortgage Broker, Evi Wyszenko! We found her when we were looking at Allworth. One of their former staff got us in touch with her - I don't really know what a diamond broker is, but apparently she is one of them. Sounds about right, she is a gem! We visited Evi yesterday just to go over our finances and to make sure we hadn't bitten off more than we could chew with the price of the house (all the bloody extras really add up!!!) and land. We're in a good position, a long way under the maximum amount we had been pre-approved for!

We first met with Evi almost one year ago, when we got the building bug. The purpose of yesterday was to go over our situation and make sure nothing had really changed. Had another look at the bank accounts, pay slips, super, all the usual stuff. The good thing about Evi, is that she genuinely is interested in your situation and doing the right thing by you. Dealing with her, I've always felt relaxed, trusting, and comfortable. She's good on the email, and so so good at explaining things to you when you are clueless like me :)

She works in Seven Hills and up near Chatswood, but if you need someone you can trust, don't let the distance deter you. We've visited her on the weekend, and she has visited us before too. She's a great person to have on your side, and has the experience of being a bank manager so she knows how things work from the other side too. She has a reputation to uphold. If you need someone to chat to about this area, keep her in mind!

Saturday, 4 May 2013

Gardens and Oran Park Construction

I talk a lot about the plants we have purchased to date. Here's a shot of most of them:

Lomandra and Liriope
Flax for front yard and Lilly Pilly for back yard
2 x Lilly Pilly for backyard on far right, 5 x Lilly Pilly for front yard to left.
Liriope, stripey white and Murraya for front yard

Stephen was installing a kitchen today (looong day!!) so Mum and I went for a drive to Oran Park with Blackie. The first thing we noticed was how much work was taking place. Not so much on the houses, but the latest releases.
Mum taking Black for a walk down Dowson. Further construction in the background-Stage 2.

View from Sales Centre Carpark, overlooking Shopping Centre
View (west) from Dowson. Just south of 5B.
Hopefully we'll have some more Eden Brae based blogs soon (we had to fork out another $750 to keep prices fixed for one more month). If anyone is interested in Oran Park on Facebook, their page is here and the community page is located here.